Short-time scheduling

 0    16 fiche    dklekowski
Télécharger mP3 Imprimer jouer consultez
 
question English réponse English
Types of short-term scheduling
commencer à apprendre
Forward scheduling and backward scheduling
Forward scheduling
commencer à apprendre
begins the schedule as soon as the requirements are known; often builds up WIP; jobs performed to customer order, schedule can be accomplished even if due date is missed
Backward Scheduling
commencer à apprendre
begins with the due date of the final operation, schedules jobs in reverse order, used in many manufacturing environments; ex. catering
Goals of short-term scheduling
commencer à apprendre
minimize completion time, maximise utilisation, minimise WIP inventory, minimise customer wait time
process-focused work centres
commencer à apprendre
high variety, low volume, mate-to-order, different materials and processing for each product, complex production planning and control, production scheduling aspects
Loading Jobs in Work Centres
commencer à apprendre
assigning jobs to work centres; approaches: input-output control, Gantt charts, assignment method
Input-output control
commencer à apprendre
CONWIP - constant WIP; for given average output rate, try to keep L low and constant then W will be short and constant; Little's formula
Gantt Load chart
commencer à apprendre
shows relative workload in facility, negatives: does not account for unexpected events, must be updated regularly
Assignment Method
commencer à apprendre
occurs in many environments: resources-jobs, planes-gates, course-rooms); type of binary linear programming model
Priority rules for Dispatching Jobs (sequencing)
commencer à apprendre
FCFS, EDD, SPT, LPT, CR
FCFS
commencer à apprendre
First come first serve; the first job to arrive at a work centre is processed first
EDD
commencer à apprendre
earliest due date; the job with the easiest due date is processed first
SPT
commencer à apprendre
shortest processing time first
LPT
commencer à apprendre
longets processing time first
CR
commencer à apprendre
critical ratio; the ratio of time remaining to required work time remaining is calculated and jobs are schedules in order of increasing ratio; CR = time remaining/work days remaining -> process jobs with the smallest CR first
Criteria to evaluate priority rules
commencer à apprendre
Average Completion Time= Sum of flow times / # jobs; Utilisation = Sum process time / sum flow time; Average number of jobs in system Sum Flow time /Sum processing time; average jobs lateness = sum late times / number of jobs