A planning heuristic for creating the WBS. This rule states that the work package in a WBS must take no more than 80 hours of labor to create and no fewer than 8 hours of labor to create.
|
|
|
commencer à apprendre
|
|
The observer interacts with the worker to ask questions and understand each step of the work being completed. In some instances, the observer could serve as an assistant in doing the work.
|
|
|
commencer à apprendre
|
|
When stakeholders create a large number of ideas, you can use an affinity diagram to cluster similar ideas together for further analysis.
|
|
|
commencer à apprendre
|
|
A scope definition process of finding alternative solutions for the project customer while considering the customer’s satisfaction, the cost of the solution, and how the customer may use the product in operations.
|
|
|
commencer à apprendre
|
|
A decision method where only one individual makes the decision for the group.
|
|
|
commencer à apprendre
|
|
This approach encourages participants to generate as many ideas as possible about the project requirements. No idea is judged or dismissed during the brainstorming session.
|
|
|
Change control system (CCS)= commencer à apprendre
|
|
Documented in the scope management plan, this system defines how changes to the project scope are managed and controlled.
|
|
|
commencer à apprendre
|
|
This subsidiary plan defines how changes will be allowed and managed within the project.
|
|
|
commencer à apprendre
|
|
A numbering system for each item in the WBS. The PMBOK is a good example of a code of accounts, as each chapter and its subheadings follow a logical numbering scheme. For example, PMBOK 5.3.3.2 identifies an exact paragraph in the PMBOK.
|
|
|
Configuration management plan= commencer à apprendre
|
|
This subsidiary plan defines how changes to the features and functions of the project deliverables will be monitored and controlled within the project.
|
|
|
commencer à apprendre
|
|
These diagrams show the relationship between elements of an environment. For example, a context diagram would illustrate the networks, servers, workstations, and people that interact with the elements of the environment.
|
|
|
commencer à apprendre
|
|
A moderator-led requirements collection method to elicit requirements from stakeholders.
|
|
|
commencer à apprendre
|
|
Most projects have a determined budget in relation to the project scope. There may be a qualifier on this budget, such as plus or minus 10 percent based on the type of cost estimate created.
|
|
|
commencer à apprendre
|
|
A requirements collection method used to elicit requirements from stakeholders in a one-on-one conversation.
|
|
|
commencer à apprendre
|
|
A group decision method where more than 50 percent of the group must be in agreement.
|
|
|
commencer à apprendre
|
|
This approach maps ideas to show the relationship among requirements and the differences between requirements. The map can be reviewed to identify new solutions or to rank the identified requirements.
|
|
|
commencer à apprendre
|
|
As with brainstorming, participants are encouraged to generate as many ideas as possible, but the suggested ideas are ranked by a voting process.
|
|
|
commencer à apprendre
|
|
The observer records information about the work being completed without interrupting the process sometimes called the invisible observer.
|
|
|
commencer à apprendre
|
|
A group-decision method where the largest part of the group makes the decision when it’s less than 50 percent of the total. (Consider three or four factions within the stakeholders.)
|
|
|
Product acceptance criteria= commencer à apprendre
|
|
This project scope statement component works with the project requirements, but focuses specifically on the product and what the conditions and processes are for formal acceptance of the product.
|
|
|
commencer à apprendre
|
|
A scope definition technique that breaks down a product into a hierarchical structure, much like a WBS breaks down a project scope.
|
|
|
Product scope description= commencer à apprendre
|
|
This is a narrative description of what the project is creating as a deliverable for the project customer.
|
|
|
commencer à apprendre
|
|
Defines the product or service that will come about as a result of completing the project. It defines the features and functions that characterize the product.
|
|
|
commencer à apprendre
|
|
A project assumption is a factor in the planning process that is held to be true but not proven to be true.
|
|
|
commencer à apprendre
|
|
A project boundary clearly states what is included with the project and what’s excluded from the project. This helps to eliminate assumptions between the project management team and the project customer.
|
|
|
commencer à apprendre
|
|
A constraint is anything that limits the project manager’s options. Consider a predetermined budget, deadline, resources, or materials the project manager must use within the project— these are all examples of project constraints.
|
|
|
commencer à apprendre
|
|
"These are the measurable goals that determine a project’s acceptability to the
|
|
|
project customer and the overall success of the project. Objectives often include the cost, schedule, technical requirements, and quality demands." commencer à apprendre
|
|
project customer and the overall success of the project. Objectives often include the cost, schedule, technical requirements, and quality demands. "
|
|
|
commencer à apprendre
|
|
"These are the demands set by the customer, regulations, or the performing organization that must exist for the project deliverables to be acceptable.
|
|
|
Requirements are often prioritized in a number of ways, from “must have” to “should have” to “would like to have.”" commencer à apprendre
|
|
Requirements are often prioritized in a number of ways, from "must have" to "should have" to "would like to have." "
|
|
|
commencer à apprendre
|
|
This defines all of the work, and only the required work, to complete the project objectives.
|
|
|
Requirements documentation= commencer à apprendre
|
|
This documentation of what the stakeholders expected in the project defines all of the requirements that must be present for the work to be accepted by the stakeholders.
|
|
|
Requirements management plan= commencer à apprendre
|
|
This subsidiary plan defines how changes to the project requirements will be permitted, how requirements will be tracked, and how changes to the requirements will be approved.
|
|
|
Requirements traceability matrix (RTM)= commencer à apprendre
|
|
This is a table that maps the requirements throughout the project all the way to their completion.
|
|
|
commencer à apprendre
|
|
The project customer may have specific dates when phases of the project should be completed. These milestones are often treated as project constraints.
|
|
|
commencer à apprendre
|
|
Undocumented, unapproved changes to the project scope.
|
|
|
commencer à apprendre
|
|
The formal inspection of the project deliverables, which leads to project acceptance.
|
|
|
Stakeholder analysis demands quantification of stakeholder objectives goals such as “good,” “satisfaction,” and “speedy” aren’t quantifiable." commencer à apprendre
|
|
Stakeholder analysis demands quantification of stakeholder objectives goals such as “good,” “satisfaction,” and “speedy” aren't quantifiable. "
|
|
|
commencer à apprendre
|
|
A scope definition approach that studies and analyzes a system, its components, and the relationship of the components within the system.
|
|
|
commencer à apprendre
|
|
A group decision method where everyone must be in agreement.
|
|
|
commencer à apprendre
|
|
As with value engineering, this approach examines the functions of the project’s product in relation to the cost of the features and functions. This is where, to some extent, the grade of the product is in relationship to the cost of the product.
|
|
|
commencer à apprendre
|
|
A WBS companion document that defines all of the characteristics of each element within the WBS.
|
|
|
commencer à apprendre
|
|
A prepopulated WBS for repetitive projects. Previous projects’ WBSs are often used as templates for current similar projects.
|
|
|
Work breakdown structure (WBS)= commencer à apprendre
|
|
A deliverables-oriented breakdown of the project scope.
|
|
|
Work performance information= commencer à apprendre
|
|
Status of the deliverables: the work that’s been started, finished, or has yet to begin.
|
|
|